CHIVAYO’S GWANDA PROJECT TO DELIVER 10MW IN SIX MONTHS

AFTER stuttering in the initial phase, the 100-megawatt
(MW) Gwanda solar project is expected to resume later this year under a new
phased implementation schedule that could deliver the first 10MW within six
months.

According to the revised implem…

AFTER stuttering in the initial phase, the 100-megawatt (MW) Gwanda solar project is expected to resume later this year under a new phased implementation schedule that could deliver the first 10MW within six months. According to the revised implementation plan seen by The Sunday Mail Business, the first phase involves drafting an amended engineering, procurement and construction (EPC)